Beijing Zhenchong Machinery Company's vibratory equipment enters Myanmar

Published Time:

2023-10-18

On September 28, 2023, the month-long after-sales service work in Myanmar was completed, and the engineer returned to China successfully on October 2.

This project used our company's 180kW vibratory compaction equipment, equipped with three 10-meter guide rods and one 3-meter guide rod, challenging the vibratory compaction and densification of sand piles to a depth of 35m. Our engineer, Mr. Jia, despite the hardships, went to Myanmar alone to complete the equipment guidance, installation, and trial operation. The project used automated intelligent pile driving recording equipment to achieve remote control of equipment start and stop, successfully applying intelligent vibratory compaction construction.